Controlled Lowering of a 600-Tonne BoilerDismantling of the Linz Power PlantAs part of the dismantling of the power plant in Linz, a 600-tonne, 55-metre-high boiler was safely and precisely lowered using the DSD strand lifting system. The boiler was lowered in 4-metre increments, allowing it to be dismantled section by section. LH200 strand jacks, together with the corresponding hydraulic and control systems, were used to carry out the lowering operation. |